RACHEL GINGERICH

Structural Option

THE DUNCAN CENTER

Dover, DE

a

General Description:

The Capstone Project Electronic Portfolio (CPEP) is a web‐based project and information center. It contains material produced for a year‐long Senior Thesis class. Its purpose, in addition to providing central storage of individual assignments, is to foster communication and collaboration between student, faculty consultant, course instructors, and industry consultants. This website is dedicated to the research and analysis conducted via guidelines provided by the Department of Architectural Engineering. For an explanation of this capstone design course and its requirements click here.

User Note:

While great efforts have been taken to provide accurate and complete information on the pages of CPEP, please be aware that the information contained herewith is considered a work‐in‐progress for this thesis project. Modifications and changes related to the original building designs and construction methodologies for this senior thesis project are solely the interpretation of Rachel Gingerich. Changes and discrepancies in no way imply that the original design contained errors or was flawed. Differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the original design.

Final Report
 
Final Report
 
 

Executive Summary

 
 
    This report evaluates The Duncan Center in Dover, DE as a concrete framed system with two-way flat slabs with drop panels and shear walls, compared to the existing moment frame steel and composite deck system.   The system was evaluated based upon structural, acoustics, and construction management analyses.
 
 

     The concrete structural system consists of typical 12” thick two-way flat slab with drop panels framed with 16”x16” columns, except the sixth floor which is a one-way slab framed with 24”x28” columns.  Shear walls with an 8” thickness support the structure laterally, except for on the sixth floor which is supported laterally by a concrete moment frame formed by the slab beams and columns.  Foundations were redesigned for the system and augercast piles were change from 16” dia. to 18” dia. with little change to pile cap configurations.

 
 

     As per the results for the analyses it was found that the proposed concrete structural system performed better than the existing steel structural system for reducing spray-on fireproofing, increasing mechanical ceiling to floor cavity space, increasing the sound transmission class, improving reverberation time, and reducing cost.  However, despite all of these benefits, the proposed concrete structural system also increases the construction schedule by six months as compared to the existing steel structural system.  Therefore, changing the structural system from steel to concrete is not recommended, as schedule is the Owner’s number one concern.

 
 

Click on the thumbnail below to see the full report.

 
 
 
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
 

Contact

This page was last updated on May 5, 2008, by Rachel Gingerich and is hosted by the AE Department © 2008