Building Statistics

 

 

 

General Project Data:

         

Building Name:  JetBlue Training Facility

         

Location and Site: 

8265 Hangar Blvd

Orlando International Airport, Orlando, FL

 

The Training Facility is being built on 13.6-acre site on GOAA property, south of the BeeLine Expressway and west of Goldenrod Road.  Access to the site is via Hangar Boulevard on the west side.  An underground high-tension line runs diagonally through the site.

 

Building Occupant Name:  JetBlue Airways Crew

 

Occupancy or Function Types: 

Ground Floor:  Business (B), Small Assembly (A-2), Factory-Industrial(F)

Second Floor:  Business (B)

Third Floor:  Business (B)

 

The Facility will encompass 100,000 sq.ft. of area to accommodate eight fullflight simulators, two cabin trainers, classrooms, cabin crew training equipment, a training pool, fire-fighting training station, and administration offices.  This will serve to continuously train JetBlue pilots and in-flight crew, along with supporting the training for its technical operations and customer service crew.

 

Size:

          Ground Floor:                   51,704 sq.ft.

          Second Floor:                   27,565 sq.ft.                  Total:  105,475 sq.ft.

          Third Floor:                       26,206 sq.ft.

 

Number of Stories above grade/Total Levels: 

3 stories above grade/ 3 Total Levels

 

Primary Project Team:

          General Contractor – Suitt Construction Company

          Owner – JetBlue Airways

Owner’s Representatives – Tishman Construction Corporation

Owner’s Architect - Rubin & Rotman Associates

            Architect/Engineer – BRPH Architects – Engineers, Inc.

 

Mechanical & Plumbing Engineer – Shappley Design Consultants

Mechanical & Plumbing Contractor – J & A Mechanical

Electrical Contractor – Tri-City Electrical

Fire Protection Engineer - Global Fire Engineering

Fire Protection Contractor – American Sprinkler Company

         

    Dates of Construction: 

Notice To Proceed – February 2004

Substantial Completion of Simulator Hall – February 2005

Construction Complete – June 2005

    Actual Building Cost:

Total Building Cost: $15 million

Simulator & Equipment Cost: $50 million (supplied by owner)

     Project Delivery Method: 

          Design/Build

         

     Architecture:

The exterior of the building will consist of composite aluminum panels in JetBlue corporate blue and grey along with architectural pre-cast concrete panels with exposed aggregate.  Aluminum curtain walls and spandrel glass will encompass areas along the west façade which will function as the main entrance.  This will present a contemporary look with strong design elements that will project a bright and airy image with large amounts of natural light in public areas. 

The interior will also bring the strong, contemporary design elements that will project a bright and inviting image for students and crew.  The main reception and areas of congregation will have porcelain or vinyl tile in shades of white, grey, and blue.  Classrooms and administrative offices will be carpeted with colors and styles complimenting the tile areas.  The main reception area and palm court will house multiple interior palm trees and a large steel and glass monumental stairway.

     Major Codes:

The Florida Energy Efficiency Code for Building Construction

The South Florida Building Code, Miami-Dade and Broward Edition             

The Standard Swimming Pool Code, 1997

The Florida Accessibility Code for Building Construction

     Zoning and Historical:

The Training Facility is being constructed adjacent to an expressway and near a main runway for the Orlando International Airport.  Along with high limitations on the building and equipment used to erect it, the Training Facility is located in a Noise Overlay District.  Noise from these adjacent airport and expressway activities is a major concern and strict noise criteria ratings for the glass had to be met.

     Building Envelope:

Foundations will be cast-in-place concrete providing the structural support for the building.  Above grade, a steel frame with a combination of glazed aluminum curtain wall, composite aluminum panels, and reinforced precast concrete wall panels will provide the building envelope.  A modified bitumen roofing over insulating concrete and rigid insulation over vented deck enclose the building.

     Electrical:

The electrical system for the JetBlue Training Facility is typical for normal power conditions.  The system consists of a main distribution panel 3 phase, 4 wire 480/270 V Primary System and a 208/120 V 4 wire, 3 phase, 4 wire Secondary System.  It also contains 2000kVA and 2500kVA,  3 phase Y main transformers.  Conduit will be run under the slab and in the walls.  Electrical will be run from the OUC electrical pull box across Hangar Blvd.

     Lighting:

Different forms of fluorescent lighting will be used throughout the JetBlue Training Facility.  Offices and classrooms are dominated by 2’x4” recessed parabolic and grid - troffer lighting on all floors.  Recessed compact fluorescent downlights are used throughout the auditorium, break room, lounge and main entrance stairwell.  The Simulator Bays and mezzanine areas are illuminated with fluorescent dome wrap and wrap around surface mount fixtures around the perimeter of the bays.  In grade ground fixtures illuminate the Palm Court area, while decorative surface mount lighting illuminates the terrace on the third floor.

     Mechanical: 

The JetBlue Training Facility has a 311-ton air-cooled chiller providing chilled water for 6 air handling units serving the Simulator Bays.  Twelve packaged roof top air handling units provide cooling for the remaining office and classroom spaces.  Heat is provided by electric coils in the VAV system.  A 3-ton split system will service the separate security building adjacent to the entrance gate. 

     Structural:

Cast-in-place spread and strip footings with a slab on grade will support the structural steel system.  Eight 2’ thick slabs will be poured to provide extra support below grade for the Simulators.  Elevated slabs will be 3” insulating concrete on rigid insulation board on 1-1/2” metal deck.  Building will be framed with light gauge steel framing with galvanized metal studs.  Galvanized Type B steel roof deck with 3” insulating concrete and a bituminous membrane will provide support and protection on the roof.

    Construction:

The Training Facility was delivered as a Design-Build project with the excavation starting in May 2004.  Substantial completion of the Simulator Bays is planned for February 2005 and substantial completion of the project is expected to be June 2005.  The building will be delivered as a $15 million project, but will end up being near $70 million once the 6 simulators and 2 cabin trainers are installed.  Initial designs were performed by Rubin & Rotman Architects for JetBlue Airways, and Suitt Construction and BRPH Architects-Engineers fully developed the remainder of the project.  Greater Orlando Aviation Authority and City of Orlando regulations must be followed and permits obtained.  Excavation at the site was fairly simple, with the relatively level ground and lack of unforeseen site conditions.

     Fire Protection:

The Training Facility involves 3 wet-pipe fire sprinkler systems, two single interlock pre-action systems and a class 11 manual wet standpipe system without hose racks.  The Simulator Bay, computer rooms, and cabin trainers will be protected by the pre-action system, and all other areas protected by the wet-pipe system.  An electric solenoid valve for the simulator bay and computer room’s pre-action system will be released by the fire alarm detection system.  Pre-action system supervisory air pressure switches shall also be monitored by the fire alarm system.  Valve tamper switches are being provided and shall be controlled by the fire alarm detection system.

     Transportation:

Dual elevators will be installed in the main portion of the building adjacent to the Main Stair.  A scissor dock lift will be installed near the electrical, mechanical, and storage for temporary storage. 

     Telecommunications:

A voice data intercom system will be installed.  A telephone room will be dedicated to the telecommunication system, and underslab conduit will carry telecommunication wires.  Basic voice and data jacks are supplied in classrooms and office spaces.  Extra services will be supplied for equipment in the auditorium, while special lines are dedicated to the simulator bay computer rooms.

This page was last updated on Friday, November 12, 2004.

This page was created by Sarah Lippai and is hosted by the AE Department.