The Global
8000 Harbour View Boulevard Suffolk, Virginia |
GENERAL
PROJECT DATA |
|
Building
Occupant |
Lockheed Martin Corporation |
Function
Types |
Use Group
B : Business Occupancy Use Group
A-3 : Assembly Occupancy |
Size |
50,000 ft2 |
Stories
Above Grade |
One, with mechanical mezzanine |
Project
Team |
Owner: LMC Properties Designer:
Applied Minds,
Inc. Architect:
DBI Architects CM
Advisor: Himes
Associates, Ltd. General
Contractor: James G. Davis
Construction Corp. MEP
Engineer: KTA Group,
Inc. Civil
Engineer: Kimely-Horn and
Associates, Inc. Structural
Engineer: Granzow Structural Engineers |
Construction
Dates |
August 2003 - November 2004 |
Overall
Cost |
$22.1 million |
Project
Delivery |
CM Agency w/ General Contractor |
ARCHITECTURE |
|
Architecture |
The hexagonally shaped Global Vision
Integration Center is roughly partitioned into six segments around a central
atrium, with four sectors dedicated to open experimentation areas, one sector
housing an auditorium, and a final sector for reception, conferencing and a
functional café. Decorative elements
include a custom fabricated lighthouse within the atrium, an illuminated dome
ceiling in the reception area and a storefront glazing system enclosing a
bowed corridor between the reception area and center atrium. |
Major
Codes |
Virginia Uniform Statewide Building Code 1996 BOCA National Building Code 1996 BOCA National Fire Prevention Code 1996 BOCA National Energy Conservation Code 1996 International Mechanical Code 1996 International Electrical Code 1996 International Plumbing Code 1992 CABO/ANSI A117.1 Handicap Code |
Zoning
& Historical |
Located within the Bridgeway
Commerce Park, the site consists primarily of heavily wooded and undeveloped
wetlands. The underlying zoning is M-1
Light Industrial, with a Special Corridor Overlay District established by the
City of Suffolk to encourage a variety of land uses, maintain architectural
uniformity and promote improved circulation. |
Building
Envelope |
The envelope consists of load-bearing
concrete tilt-up panels with inset storefront glazing and three concentric
elevated roof levels separated by clerestory windows. Skylights are located around the corners of
the hexagonal perimeter and over the central atrium. |
BUILDING
SYSTEMS |
|
Electrical |
The electrical system is designed for total
loads in excess of 1,800 KW, with the main switchboard rated at 2,500 A, 3
phase, 277/480 V. While no redundant
systems have currently been specified, provisions for a future diesel fired
generator and UPS system have been incorporated into the design. A concrete encased duct bank leading from
the future generator pad to the main electrical room is planned for eventual
expansion. |
Lighting |
Interior lighting is a combination of
low-bay metal halide, strip fluorescent and incandescent downlights. Complex dimming controls are used to balance
the intensity of incandescent fixtures and natural light entering office and conference
areas from clerestory windows. |
Mechanical |
The HVAC system is composed of five air
handling units on the mechanical mezzanine that feed low pressure spiral duct
and VAV boxes throughout the building.
Cooling was provided by three chillers located within an enclosed yard
against the rear property line. Unit
heaters along the building perimeter offered dedicated heating for
high-traffic vestibule and entry areas.
The main electric, telephone and water rooms are located beneath the
elevated slab in the rear of the building and separated by concrete masonry
walls. From the main rooms, services were
routed to the mezzanine where they were disseminated outward to service all
six sectors. |
Structural |
The building is supported by a foundation
of driven precast piles, with subsequent
cast-in-place pile caps, grade beams and slab-on-grade. The superstructure is comprised of steel
pipe columns, custom pipe trusses and open-web joists spanning open bays. Metal decking is used as a low-pitch roofing
base and as part of the composite slab on the mechanical mezzanine. Architectural-grade tilt-up concrete panels
form the exterior load-bearing support and façade for the building. |
Fire
Protection |
A wet pipe sprinkler system provides
coverage the open-bay, atrium and conference areas in the building, while a
pre-action system was used within the computer rooms. Duct-mounted smoke detectors and graphical annunciator panels allow for early detection and control
during emergency situations. |
Transportation |
As a single-story project, the building
includes no special conveying systems.
Two prefabricated steel stairs are installed on opposing sides of the
building, allowing service access to the mechanical mezzanine |
Telecommunication |
Electrical and telecommunications wiring
are distributed horizontally on cable trays and then into electrical metallic
tubing for covering vertical distances.
Evenly spaced floor receptacles are adaptable and make data or voice
services readily available in open-bay areas. |
This page was last updated on Sunday, October 31,
2004. This page was created by Bryan
Franz and is hosted by the AE
Department. |