— BUILDING STATISTICS

PART 1: GENERAL PROJECT DATA

 

General Data:
Building Name
Institute of Contemporary Art (ICA)
Location and Site 100 Northern Avenue, Boston, Massachusetts
The Institute of Contemporary Art is located along Southern Boston's harbor. It is just one of nine buildings proposed to be built on the 13 million square foot site known as Fan Pier.
Latitude: 42.4 degrees
Longitude:   71.0 degrees
Elevation:   approximately 30 feet
Building Occupant Name The new waterfront building will be the primary home for the Institute of Contemporary Art (ICA) in an attempt to shelter its unparalleled growth rate over the last five years.  The ICA is a non-profit institution devoted exclusively to the presentation of contemporary art and has earned its place as one of New England’s most vibrant cultural organizations.  Through a comprehensive schedule of exhibitions of local, national, and international significance and a program of educational outreach, the museum provides the public access to contemporary art, artists, and creative processes.        
Occupancy / Function Types

The Institute of Contemporary Art consists of a myriad of different function types including: Lobby, Dining Room, Retail, Reheat Kitchen, Office, Classroom, Bookstore, Library, Theater, and Meeting Room.

Building “Use” Groups Assembly (A-3)
  Offices and Classrooms (B)
  Bookstore (M)
Type of Construction Type 2A Construction
Size Building Height:              69’-11”
Overall Project Size:      65,000 ft2
First Floor Area              11,055 ft2
Second Floor Area        8,895 ft2
Third Floor Area             6,425 ft2
Fourth Floor Area          18,450 ft2
Mezzanine Area             2,575 ft2
Stories Above Grade / Total Levels 4 above grade plus Mezzanine, 0 below grade due to close proximately to harbor  

 

Primary Project Team:
Developer

Spaulding & Slye

Client      The Institute of Contemporary Art     
Contractor Macomber Builders, Boston    
Design Architect  Diller + Scofidio         
Associate Architect  Perry Dean Rogers Partners  
Structural   Arup New York, Arup London
MEP/FP Arup New York   
Lighting  Arup London, Arup New York 

 

Other Consultants:
Acoustics Consultant Jaffe Holden Acoustic  
Theater Consultant  Jules Fisher/Joshua Dachs Assoc.        
Code Consultant Rolf Jensen Associates  
Spec Writer   Kalin Associates     
Civil Engineer Parsons Brinckerhoff   
Cost Estimator Hanscomb 
Landscape Architect Michael Van Valkenberg     
Vertical Transportation Arup New York     
Enclosure 

Simpson Gumpertz & Heger Inc      

RA Heintges Assoc.  

AV Engineering Shen Milsom Wilke     
Media Consultant  Ear Studio      
Geo Tech Engineers Haley & Aldrich, Inc    
Security Consultant Steven R. Keller & Associates, Inc.        
Structural Review  Souza True & Partners  

Dates of Construction:
Schematic Design February 4, 2002
Bid Date May 28, 2004
Start Date   June 1, 2004
Substantial Completion March 14, 2006
Construction Duration  22 Months

Actual Cost Information:
Overall Estimated Costs $40,000,000
Construction Contract $35,460,814
HVAC Contract $5,060,000
Electrical Contract $4,312,000
Plumbing Contract $477,000
Fire Protection Contract $261,000 

Project Delivery Method:
Project Delivery Method

Design Build

 

Architecture:
Architecture

The bold architectural statement from Diller & Scofidio along with a dramatic waterfront location entwine to produce a vibrant, high tech center for thought provoking showcase space, performances, and instructive activities.  The Institute of Contemporary Art anticipates developing and displaying a diverse permanent collection of art comprised in various media formats which has acted as the driving catalyst for the architectural program.  The ICA anticipates receiving individual works and complete traveling exhibitions to be displayed in the new building including sculpture, paintings, and drawings.  Video and projection pieces may be shown, either as interpretive material accompanying a show, or as art pieces in their own right. 

 

Viewing these works of art in natural daylight was a prime objective of the institution and consequently influenced many of the architectural components comprising the new Institute of Contemporary Art.  North facing skylights will facilitate natural light throughout the building’s main gallery halls which will be located on the 4th floor.  Flexibility was key in designing the interior program.   Lighting systems were designed to respond effectively and economically as layouts and displays are changed and also to protect artwork from being damaged or faded by exposure to ultraviolet light.  The ICA will be graced with an array of lights, illuminating a “floating box” and radiating a warm, welcoming waterfront persona. 

 

Numerous architectural explorations eventually led to a design surprisingly sensible and straightforward: a steel-frame box building with a column-free 4th level that will radically cantilever out over Boston’s harbor.  The cantilevered design embraces a public harbor walk and produces ever-changing panoramic spectacles of the water's edge.  Collaboration between architect and engineer early in the design process resulted in a highly efficient structure in which structural elements have been fused to create architecture.  This planning will result in a 65,000 ft2 building which appears to float above land and sea.   

Codes and Standards

Massachusetts Fire Prevention Regulations

Massachusetts Electrical Code

State Building Code, Commonwealth of Massachusetts - 6th Edition, effective 2/28/97

American Concrete Institute ACI 318-95 as modified by 780 CMR 19

American Institute of Steel Construction as modified by 780 CMR 2:

American National Standard Institute (ANSI)

American with Disabilities Act (ADA)

NFPA 70 National Electrical Code (NEC) with 527 CMR 12.00 Amendments (1999)

National Electric Safety Code (NESC)

Occupational Safety and Health Administration (OSHA)

Underwriters Laboratories (UL)

Massachusetts General Laws

ASCE Manuel of Engineering Practice No. 67, “Wind Tunnel Testing for Buildings”

Unified Soil Classification System (ASTM D2487)

Zoning and Historical Information

Design and construction of a new museum in Boston is an uncommon incidence and opportunity.  The new building for the ICA will be the first art museum to be built in Boston in almost 100 years and is destined to embody the architectural potentials of the nations most historic cities.  In that milieu, it is anticipated that the design creates a pioneering breakthrough museum for art of the 21st century. 

 

The planners and designers envisioned an affordable structure with a striking profile, situated on a small lot atop a reclaimed landfill on the shore of Boston Harbor—one that would incorporate the harbor’s shoreline walkway into the ground floor while boasting a contiguous gallery above.  With structural and architectural challenges closely intertwined, the project’s architects at New York-based Diller + Scofidio invited engineers from Arup New York to participate early on in the conceptional phase.

 

Fan Pier, at 13 million square feet, makes it the largest proposed private development project on the Southern Boston Waterfront.  The land is owned by the Chicago-based Pritzker family and is inherently a key piece of Boston's industrial land.  The Institute of Contemporary Art is just one of nine buildings proposed to be built along this waterfront land.  In order to obtain the proper permits, developer Spaulding & Slye agreed to construct parks, water transportation, and other publicly accessible buildings during the first stages of the Fan Pier development.  These public amenities, including the Institute of Contemporary Art, must be completed early in what could be a decade or more of phased construction. 

 

A height limitation of 70 feet was imposed early on in the design of the ICA building in order to escape the title and classification of a high rise.  This effort was achieved so that additional codes and regulations could be avoided.

Building Envelope The exterior envelope of the new Institute of Contemporary Art is composed of identically sized vertical planes of transparent glass, translucent glass, and opaque metal.  The use of transparent glass facilitates a natural daylight viewing area while the use of opaque metal responds to the functional requirements of the interior plan.  These elements obscure the division between windows, walls, and doors while at the same time giving an impenetrable, seamless, and taught skin capable of protecting cherished contents from climatic conditions along Boston’s coastline.  Along the North side of the 4th floor exhibition space spans a lenticular glass curtain wall, which is composed of minute vertical lenses.  These lenses eliminate glare by blocking all light except that which is viewed perpendicular to the surface.  The theater, located on the second and third floor, boasts a full complement of clear glass glazing which frames a dramatic backdrop with a harbor view.  These walls respond to strict performance needs by translating from filtered luminosity with no panoramic view to complete blackout.  Four massive trusses-made from welded W section beams-grace the exterior through a silhouetted appearance behind the main gallery’s translucent facade.  Extensive overhang details due to the cantilever of the structure facilitate the building envelope to run beneath the building as well as on top.  The roof is composed of flat EDPM with an extensive assortment of north facing skylights while the underside is made up of wood that mirrors the harbor walkway.  Overall, the envelope of the new Institute of Contemporary Art has been carefully designed to produce a welcoming and dramatic waterfront presence. 

PART 2: BUILDING STATISTCS

Electrical:
Utility Service A single 480V, three phase, 4 wire service will be provided by the local Electrical Utility Company to power the building. The transformer is mounted outside at grade on a pad. A “Standard Service” type of 2500 amps @ 480V, 3 phase is provided.
Electrical Service Electrical service will be taken from the utility transformer through to the main 480V switchgear. 480 V power is then distributed to the electrical closets via cable feeders. Vertical distribution is via electrical riser closets. 277V/480V and 120V/208V is then distributed from panel boards to loads within the building via branch circuits. The café and kitchen areas will have their own metered feeders. UPS power for communication, security, and building management systems equipment along with raceways for audio-visual, secretly voice, and data systems are provided. The elevators have their own disconnect switch for lighting and power. The main copper bus is grounded to the main cold water pipe and grounding rods. Steel columns will be grounded with grounding rods around the perimeter of the building.
Emergency Generator A 350 kW emergency diesel generator, located on the first floor, is installed in an open frame, air cooled, skid mounted, and provided with a critical silencer. The skid assembly is installed on spring loaded vibration isolators for additional sound control. The generator will draw from a 200-gallan sub-base, double walled fuel oil tank. The 200-gallon tank is the largest that code will allow on site. The generator will provide approximately seven (7) hours of fuel autonomy at full life-safety loading. Each floor has a designated ‘emergency’ electrical closet and emergency power is distributed from panel boards within.

Generator Loads:
Building’s Management System
Fire Alarm System
Egress Lighting
Electrical / Mechanical Room Lighting
Elevator Recall and Disable Egress
Emergency Communications
Public Address
Security Systems
Atrium Smoke Control

Fire Alarm System The fire alarm system is fully addressable and designed for ordinary and light hazard classification of building. The Staff Entry holds a fire command station, remote annunciation panel, controls for air handling equipment, and smoke control/purge. Fire alarm annunciation will be via voice alarm in all program areas assessed as at risk including art display, art storage, mechanical/electrical rooms, elevator shafts and machine rooms.
System Redundancy A second contingency feeder is provided by Utility so that a failure of any single utility network feeder will not interrupt power to the building. A single fault tolerance at the point of connection to the building will provide for additional redundancy. Emergency power is distributed independently of normal power system raceways. UPS power via distributed local units are applied to essential building systems.

Lighting:
Overall Design

The lighting scheme addresses the following key requirements:
• Flexibility is of fundamental importance
• Lighting systems must respond as layouts and displays change
• Flexible in achieving optimum lighting levels and light distribution
• Utilizes both daylight and electric light where appropriate
• Flexible in space planning
• Suitable for the conservation of all artworks
• Easy and inexpensive to operate and maintain
• Energy Efficient
• Keep the ceilings as uncluttered as possible
Interior power allowance of 1.6W/ft2 complies with Massachusetts State Building Code and ASHRAE Standard 90.1.

Artwork Conservation The lighting scheme is designed to avoid damage or fading by exposure to light based upon the following principles:
Sensitivity of the artwork to light
• Level of illumination
• Period of time over which artwork is exposed to illumination
• Spectral content of light including ultraviolet
Non-Public Areas Non-public areas are predominately lighted through high efficiency, fluorescent fixtures with occupancy sensors where additional energy savings can be realized. Mechanical/electrical rooms, stairways, and corridors are designed at 20 foot-candles and serviced with pendant mounted industrial type 4-feet fixtures while utility rooms and office break rooms are set at 30 foot-candles. Lamps possess the following characteristics: rapid start, T-8 fluorescent, electronic ballast, high power factor, and a color temperature of 3500k. Self-powered LED exit lights are included.
Gallery Design A balance between increased illumination for easier viewing and conservation of artwork by limiting exposure to light is a primary focus for lighting of the 4th floor galleries. Fixtures were selected based on color temperature and color rendering properties of the light sources. For all display spaces, fixtures with a color-rendering index of 90 or greater are specified. All surfaces in the Gallery are finished with a neutral matte, white color. Lighting fixtures were also chosen with respect to their uniformity of illumination. Directional lights, via track lighting, are positioned to produce lighting angles of between 25-40 degrees from the art at eyelevel in order to reduce glare. A bus track is included with anticipation of supporting greater lighting loads, power taps, and small hanging loads. The Gallery floor is kept low to avoid bright reflections of the floor in some artworks. Diffusing layers on the inside of windows and illumination of building exteriors combine to minimize distracting reflections of the interior. Sub-division of the galleries through the use of walls and display cases has been accounted for in the lighting plan. All light sources in display spaces have a low direct heat radiation factor to avoid damage from excess heat. Linear fluorescent fixtures are fitted with Filter-Ray acrylic UV filters while track lighting are fitted with Optivex glass UV filters. Direct sunlight has been minimized through a diffusing ceiling material and north-facing skylights.
Daylight Design Daylight is used to provide ambient background light because of the following reasons:
• Good color rendering because of more compete color spectrum
• Energy savings
• Contact with the external environment gives an awareness of the external environment and time of day.

The daylight delivery system consists of a series of horizontal north-facing skylights. The advantage of this system are that changes in direct solar radiation on the roof are dampened out. The skylights include a perforated reflector that improves ceiling luminance uniformity by reducing light towards the south and increasing light toward the north. The 4th floor galleries have translucent ceilings made up of specially formulated fabric. This fabric is 100% Trivera CS and white in color producing a visible light transmission of at least 70%. Mechanical blackout shades, linked with the building control system, provide for the optimum amount of light passing through the skylight system.

Long Gallery (North Facing) Along the north side of the building runs a long gallery in which light levels will exceed recommendations for art conservation. To minimize this negative effect, the glass is composed of an angular cut-off film and a UV blocking PVB interlayer. In addition, motorized black out shades are utilized to mitigate direct solar radiation on the glazing until 10:30AM.
Temporary Art Storage There are no rooms for primary storage of art on the premises of the new Institute of Contemporary Art. However, temporary art storage facilities have been justified into the interior plan and are accounted for in the lighting design. The design includes the following parameters:
• Ultraviolet protected luminaries
• 500 lux/50 foot candle are provided for temporary viewing of specific artwork for removal.
• Lighting turned off automatically when facilities are not in use
Main Lobby Spaces are sensitively lit with approximately 200 lux / 20 foot-candle to allow for easy visual transition between spaces. Linear fluorescent luminaries with an opal glass covering and an integral adjustable tungsten halogen downlight provide for lower level lighting. In addition, round adjustable in-grade uplights along the glass and wall illuminate the lobby ceiling. The lighting controls are located next to the security office ticketing desk.
Theater The peak demand load for the theater is assumed at 288 Kw. It has been designed with a diverse range of activities from lectures to performances. The architectural lighting in the Theatre responds to the outside through extensive use of glazing. Minimizing glare was of prime concern to the designers involved. Approximately 150 lux / 15 foot-candle of light on the floor is provided for occupants to find their seats. While viewing a presentation or performance, 30 lux / 4 foot-candle of light is given minimizing spill light upon projection screens. To be consistent with exterior lighting conditions, the theater ceiling is up lit using asymmetrical floodlights mounted to a pipe grid. Square downlights recessed into the ceiling provide for additional illumination.
Dinning Room The dinning room is coded as a light refreshment service facility to avoid extra code requirements associated with a destination restaurant. Direct sunlight is avoided while producing average lighting levels of 200 lux / 20 foot-candle. Adjustable tungsten downlights are used to accomplish this criteria.
Office Areas Indirect pendant fixtures provide 30 foot-candle on working surfaces. Direct task lamps provide additional luminance.
Emergency / Security Lighting Emergency lighting is not illuminated during normal gallery opening hours. Security lighting maintained during off-peak times throws less than 5 lux / .5 foot-candle. Emergency lighting is comprised of 2 foot nominal linear T5HO fluorescent incorporated into the gallery ceiling track system. Emergency luminaries are circuited to the emergency generator as well as having battery backup capability.

Mechanical:
Cooling System Two (2) chillers operating in parallel and located on the center spine roof cool the Institute of Contemporary Art. The total estimated chiller load is 280 tons while each chiller is sized for 140 tons or 50% of the total cooling capacity. Chillers are acoustically lined to meet strict noise mitigation criteria. The chilled water is a 35% mixture of propylene glycol and is supplied to the building at 45°F and returned to the chiller at 55°F. Two (2) variable volume pumps sized at 830 GPM distribute chilled water throughout the building.
Heating System Two (2) gas-fired low temperature hot water boilers located at the 4th floor Mezzanine Mechanical Engineering Room provide building heating. Each boiler is sized for an output capacity of 1500 MBH and comprises 70% of design heating load. Low temperature hot water is distributed to perimeter finned tube radiation. Heating hot water will be circulated using a primary-secondary pumping system with temperature reset based upon outside dry bulb temperature. Variable volume secondary pumps are powered via variable speed drives. The heating hot water is supplied to the building at 180°F and returned to the boilers at 160°F. Two port modulating control valves are provided at all terminal devices including air-handling units heating coils, fan coil units, and hot water unit heaters. Heating hot water will also flow through hot water coils and preheat outside air being supplied for ventilation through the air-handling units.
Humidification System Stringent humidification is required in all the permanent and temporary galleries. Moisture, in the form of steam, is added to the air stream to achieve the required humidity level. Two (2) natural gas fired steam generators located in the Mezzanine Mechanical Engineering Room will generate this steam. The first steam generator is rated at 138 lb/hr while the second is rated at 345 lb/hr. Two (2) such generators are used to provide low load control and a measure of system security. Stainless steel will comprise the steam supply and condensate return piping. The two (2) air-handling units serving Gallery spaces are equipped with a direct steam dispersion grid and control valves. All four (4) air-handling units have dedicated humidification sections built into them.
Air Handling Systems The Institute of Contemporary Art is divided into five (5) major zones.
Zone 1: Permanent Gallery and North Gallery (half of the space) on 4th floor
Served by a 21,140 CFM constant air volume air-handling unit (AHU-1) located on the Center Spine Roof. The unit includes particulate filters, preheat, reheat and cooling coils, humidifiers, supply, and return fans. Airside economizer is used to allow energy conservation during non-peak outdoor conditions.
Zone 2: Temporary Gallery and North Gallery (half of the space) on 4th floor
Served by a 20,800 CFM constant air volume air-handling unit (AHU-2) located on the Center Spine Roof. The unit includes particulate filters, preheat, reheat and cooling coils, humidifiers, supply, and return fans. Airside economizer is used to allow energy conservation during non-peak outdoor conditions.
Zone 3: Lobby, Retail, Administration, and Dining Room on 1st, 2nd, and 3rd floors
Served by a 31,500 CFM variable air volume air-handling unit (AHU-3) located on the Center Spine Roof. Air is distributed to different zones through variable air volume boxes, which vary the amount of air supplied to each zone based upon its cooling or heating needs. The unit includes particulate filters, preheat, reheat and cooling coils, humidifiers, supply, and return fans. Airside economizer is used to allow energy conservation during non-peak outdoor conditions.
Zone 4: Theater on 2nd and 3rd floors
Served by a 22,500 CFM constant air volume air-handling unit (AHU-4) located on the Center Spine Roof. The unit includes particulate filters, preheat, reheat and cooling coils, humidifiers, supply, and return fans. Airside economizer is used to allow energy conservation during non-peak outdoor conditions.

Zone 5: Mediatheque on 4th floors
Served by a 4,090 CFM air handling unit (AHU-5) located in the Mezzanine Mechanical Engineering Room.

Plumbing Domestic water system is brought into the Utility room (southeast portion of the building) through the municipal water main. The point of entry is greeted with a water meter. A duplex booster pump package is used to pressurize the building system. A gas fired water heater located at mezzanine level maintains water at 110°F. This hot water system is equipped with re-circulation pumps. The storm drainage system is designed based on a 100 year storm at an intensity of 4 inches per hour. The sanitary drainage system is designed to maintain at least a 1% slope per foot and 2 cubic feet per second velocity on the system.

Structural:
Foundation All loads are resolved into deep driven piles at ground level. These piles are comprised up of 11,000 linear feet of 215-ton H-section bearing piles and rely solely on soil friction to carry the building’s load. Due to the corrosive properties found at the site, a corrosion epoxy is applied to the piles up to 60 feet deep. An impressed current cathodic protection system has also been implemented to prevent corrosion. Ground beams are supported at pile cap locations. Ground Slabs are designed as suspended slabs spanning across ground beams allowing for settling of the soil beneath them over time.
Cantilever The Institute of Contemporary Art has a striking fourth level cantilever that demands attention. The 84-foot cantilever achieved with the utilization of four mega-trusses (25ft depth) with a 96 foot back-span. The trusses are each supported by two mega-columns.
Roof A lightweight triangular truss roof allows for both the dispersion of daylight as well as the distribution system for the MEP services. North-facing skylights create a 6ft wide void in the roof system.
Gallery Gallery space load is distributed by eight mega-columns positioned at the south edge of each truss and 96 feet in along the back span. Below the gallery the interior program divides in two halves by a central core strip of elevators and stairways. The east side utilizes typical structural composite steel framing.
Theater On the west side of the structure is an inclined theater, with steps from grade level to the second floor on the exterior of the building, a flat stage area on the second floor, and inclined seating from the second to the third floor. The theater is supported, along the West, by cable hangers suspended from the western mega-truss, creating a column-free lobby below the theater. The lobby is framed with ground slab and grade beams. Columns for supporting the inside of the theater are located along the east edge of the ground floor lobby and extend up to the stage and inclined seating. The floor systems of the theater, 2nd, and 3rd floors are comprised of composite steel deck.

Construction:

 

Fire Protection:
General The building is fully sprinklered with wet type sprinkler heads protecting all building areas. The gallery spaces present an interesting fire protection application as the ceiling is composed of a combustible material and equipped with the concealed type sprinkler heads in the ceiling as well as pendent sprinklers above the ceilings. This creates a double layer of heads necessitated by the existence of large skylight depths. The building is predominately light hazard with some areas considered by NFPA13 as ordinary hazard. Areas of light hazard are protected with standard type quick response sprinkler heads while areas of ordinary hazard are protected with standard response heads. The system includes Siamese, two class II fire standpipes and one combined standpipe/sprinkler risers. The building is below the high-rise level of 75 feet and thus minimum pressure requirements were reduced. Hydrant flow tests revealed a static pressure @ 67 PSI, residual pressure @ 62 PSI, and a flow of 868 GPM.
Atrium Smoke Management Philosophy The Institute of Contemporary Art consists of an atrium approximately 60 feet high and thus must meet special requirements for this kind of space. Smoke extraction is taken through the architectural roof of the atrium via ductwork and three (3) 52,000 CFM roof-mounted fans. These fans are powered from the emergency generator and will be activated by smoke detectors automatically in the event of a fire. Makeup air is provided at the bottom of the atrium utilizing two strategies:
• By automatically opening windows on the southern façade of the lobby
• By automatically opening the doors in the dining room of the restaurant
• By reversing return fan motors so they operate like supply fans

Transportation:
Vertical Transportation Two geared passenger elevators meet the vertical transportation demands of the Institute of Contemporary Art. A public elevator with dimensions of 18’X10’ and a net lifting capacity of greater than 20,000 lbs runs from the lobby up to the 4th floor gallery. Its speed is rated at 150 feet/min. A staff elevator with dimensions of 7’X6’ and a net lifting capacity of greater than 3,500 lbs runs also runs from the lobby up to the 4th floor gallery. Its speed is rated at 350 feet/min. The total height traveled by these two elevators is 45’-6”. A 750 pound capacity combination wheelchair lift and collapsing stair is located at the projection booth.
Outside walkways A large cantilever off the northern side of the building embraces a public harbor walkway. This wooden walkway flirts with the waters edge while providing access to both the north and west side of the Institute of Contemporary Art. Walkways along the Eastern and Southern exposures are standard poured concrete and connect to provide 360 degrees of free movement around the outside of the building. Emergency vehicles may access these sidewalks during an emergency by a gate set on the Southeast corner of the building.
Parking A 200-space parking lot is provided just South of the building. Access to the building is through a 1st floor atrium directly off of the parking lot. Patrons can be dropped off via a loading and unloading area next to the main entrance. In addition, goods and services are supplied via a loading dock along the Eastern side of the building.

Telecommunications
Cabling Hubbell Category 6 structured cabling system
System uses Mohawk GigaLAN four pair UTP
Purpose: to integrate all the voice, data, video, and imaging low voltage signals onto a common distribution platform
Audio Visual System Furnished audio visual, control, projection, lighting, speaker, touch screen, display, teleconferencing
Projectors, monitors, plasma displays, video control system
Harmonic load isolation transformers
Isolated grounding system for all audio technical power system panels
Speaker array, Proscenium speakers, sub woofers, portable sound reinforcement, surround sound, infrared hearing assistance system.
Security Complete CCTV, Card Access Control, Intrusion Detection, Intercom, and related systems
Proximity card reader stations
Access control door processing panels
Video Display/ Local PC for system programming
Electrochemical batteries
Cameras, Day/Night, High-Resolution,
Digital video recording system
Magnetic contact door switches
Passive infrared motion detectors
Glass break detectors
On-floor water sensors
Burglary control/communicator
Alphanumeric LCD Display keypads

Acoustics (Special Systems)
Programming The building houses a 300-seat theater and related support spaces which will play an important role in making the Institute of Contemporary Art a success for the many people who will use it. Acoustic design takes into account a wide variety of programming including film, video, jazz, new music, dance, lectures, symposia, and theater. Adjustable acoustically absorptive elements have been incorporated to lower the reverberation times and attenuate unwanted sound reflections from the glass and other wall surfaces.
Room Volume / Shape / Surface Treatment The main uses of the theater necessitates room acoustics that are fairly ‘dry’ constituting a low design reverberation time of between 0.8 to 1.4 seconds at mid frequencies. High levels of speech intelligibility for the audience results. Glass coving house-left and upstage posed challenges for controlling unwanted reflections. Absorptive material with thicknesses of two to four inches are distributed on the ceiling and rear walls of the theater to achieve desired reverberation times. Music events requiring sound control have been accommodated through the use of small, portable acoustic shell/screen elements that promote the transfer of sound energy from the stage into the audience. A series of acoustical reflectors have been placed over the stage and front row seating areas to enhance onstage hearing. Concrete flooring has been implemented as a hard reflective surface in the audience while the stage floor is comprised of resilient wood construction. A series of roll-up banners along the side walls allow for additional control of reverberation time, acoustic reflections, and sound energy density.
Noise Issues The site is impacted by a number of unwanted environmental noise sources including vehicular traffic, watercraft, and air traffic. Special attention has been paid to acoustical separation between adjacent spaces and noise making equipment in the facility, and to isolate outside environmental noise. The exterior wall consists of a double-glazed partition system (3/4 inch thick laminated inner layer with ½ inch laminated outer layer) in an attempt to avoid resonances frequently encountered with single-glazed systems. Sound and light locks with sound absorbing finishes and gasketed doors have been implemented at all theater openings. The roof consists of 8 inch thick concrete roof deck over entire seating area and stage.
Mechanical System Noise & Vibration Control Design of the heating, ventilation, and air conditioning (HVAC) equipment is designed to meet the following background noise goals:

Space NC Rating

Theater Seating Area & Stage NC-20 to 25
Sound/Lighting/Projection Control NC-25
Lobbies NC-35
Green Rooms NC-35
Dressing Rooms NC-35
Conference and Board Rooms NC-35
Performers Lounges NC-35
Administrative and Staff Offices NC-35
Performer Work Areas NC-35

Building Automation / Controls (Special Systems)
System Architecture Stand-alone intelligent DDC-control panels connected via a bus/ring network (peer-to-peer) and network controllers.
DDC control panels of modular design located in the MER at the 4th floor Mezzanine
DDC control panels for rooftop HVAC equipment
System supervisor multi-user, multi-tasking workstation connected to the DDC control panels network
Capability of performing all supervisor functions via laptop
Capability for remote access to the BMS via Web Browser Interface
Intelligent unitary DDC controllers distributed in the space, networked, and connected via network controllers
Full graphics package to facilitate operator usage
Pager notification system
System Controls Building chilled water distribution system
Building hot water distribution system
Humidification / Dehumidification system
Air-handling units
VAV boxes and Fan Coil Units
Heating and ventilating units
Exhaust fans
Integration with Lighting Control System
Programmed start-stop of systems
Monitoring of gallery conditions (temperature and humidity)
Critical Alarm Annunciation
Preventative maintenance alarms
Sequential start-up of plant following power loss
Operating logs
Trend logs and forecasting
Typical air handling unit control and monitoring
Lighting Controls The lighting control system includes occupancy sensors, programmable time clocks, photocell sensors, relay control panels, and dimmer panels. Further separate lighting controls are provided for gallery display lighting system, lobby, ground floor public spaces, and boardroom, theatrical, and auditorium lighting.

Blackout shades for the 4th floor naturally lighted environment are also controlled by the building automation system. The blackout shades are programmed to block daylight during hours that the galleries are closed including early morning and late evening. Lowering or raising the shades makes seasonal adjustment. This system protects artwork from summer overexposure and allows work to be fully illuminated during winter. Lighting levels can be adjusted in specific parts of the gallery by controlling individual shades or by controlling a grouping configuration.

Easy control of the electric lighting control zone is via programmable control switching panels. Two programming jacks are located in each of the East and West Galleries. A laptop personal computer can be plugged into the system’s jacks.

Mechanical Controls Remote start/stop
Temperature control: Modulation in sequence via a PI control loop of the heating coil control valve and the cooling coil control valve, to obtain the temperature set point of the supply/space. Use of reset cascade control where appropriate.
Humidity control: The humidification shall be modulated to maintain the design gallery and theater conditions at set point. In the event that the supply air humidity rises above 90%RH a critical alarm shall be initiated at the BMS console and the humidifier shall shut down through hardwired connection to humidity switch.
Dehumidification Control: If the gallery exceeds set point, the cooling coil valve shall be removed from the temperature control sequence and modulated to bring gallery humidity conditions back to set point. During the humidity override control, the reheating coil valve shall be modulated by the temperature control loop to maintain the supply air discharge temperature set point.
Variable volume control: supply fan speed control to maintain the static pressure set point. Fan tracking - return fan speed control via airflow measurement.
Minimum fresh air control of outside air, return air and spill air dampers. Outdoor air will be varied in response to measured CO2 levels and based on occupancy.
Economizer controls (enthalpy override) for free cooling.
Control of relative humidity.
Freeze protection interlocks.
Fan status.
Set point adjustment.
Addressable, networked VAV-boxes controls and FCU controls.
The electrical installation associated with the BMS shall be in accordance with the applicable requirements of the Electrical Sections of the project specification.
Sprinkler/Standpipe Controls A low-pressure switch will be installed on the fire protection water main as it enters the building. A trouble signal will appear at the fire alarm control panel if the pressure drops below 20 psi.
A trouble signal will appear at the fire alarm control panel if any tamper switches are activated. All control valves will have tamper switches.
Activation of any tamper switches will also signal operations via the valve-closed relay.
In the event that a sprinkler fuses, the pressure in the system will drop and the sprinkler system will activate.
An alarm signal will appear at the fire alarm control panel upon water flow. Flow switches will be located at each standpipe sprinkler feed for each floor, at the base of each standpipe riser.
Life Safety Controls Upon activation of any manual station or the automatic actuation of any smoke or heat detector, water flow switch or any other approved alarm initiating device will result in the following:
Cause the transmitter or transponder to transmit an alarm signal onto the main Fire Alarm system console. The alarm signals shall be as follows:
Sound fire alarm signal or voice evacuation message to all areas of the building.
Activate flashing visual strobes.
The fire alarm will sound until the signals are silenced. All visual strobes will flash until the system is reset.
Shut down all mechanical ventilation units.
Unlock all fail safe locked doors.
The system Alarm LED will flash.
Initiate elevator recall.
The LCD display will indicate all information associated with the fire alarm condition, including the type of alarm point and its location within the protected premises.
Activate house lighting and shut down audio equipment within the theater.
Printing and history storage equipment will log the information associated with the fire alarm control, along with the time and date of occurrence.

» Back To Top

This page was last updated on Wednesday, October 27, 2004 .

This page was created by Dustin M. Eplee and is hosted by the AE Department.