Sears Centre Thesis Project Progression Log
Progress Log
| Date | Announcement |
| Current Status | Newest announcement are added to the top |
| 4.24.06 | Senior Thesis Complete |
| 4.23.06 | ABET, Course & CPEP Reflections Posted |
| 4.10.06 | Sears Centre Thesis Presentation |
| 4.3.06 | Final Report Posted |
| 4.2.06 | Final Report Formatted |
| 1.26.06 | Thesis Schedule Posted |
| 1.21.06 | "DBOM" Questionnaire |
| 1.12.06 | Updated Thesis Breadth |
| 1.10.06 | Contact CIMCO Refrigeration |
| 12.12.05 | Thesis Proposal Posted |
| 12.5.05 | Request Research Topics |
| 11.21.05 | Technical Assignment #3 Posted |
| 11.9.05 | Problem Identification Posted |
| 11.6.05 | Technical Assignment #2 Posted |
| 10.19.05 | Critical Industry Issues Posted |
| 10.12.05 | PACE Roundtable |
| 10.6.05 | Building Abstract Posted |
| 10.5.05 | Technical Assignment #1 Posted |
| 9.28.05 | Review Contract Exhibits |
| 9.27.05 | Obtain Civil Drawings and Site Layout |
| 9.20.05 | Resume Posted |
| 9.15.05 | Technical Assignment Distributed |