Welcome to Caitlin Ferrell's AE Senior Thesis e-Portfolio
Progress Log
Time Table
| Week # |
Section to Complete |
| 1 (January 9) |
Trusses (Research) |
| 2 (January 16) |
Loads and Design Floor Systems |
| 3 (January 23) |
Design Trusses |
| 4 (January 30) |
Design Columns |
| 5 (February 6) |
Design Columns |
| 6 (February 13) |
Lateral Loads |
| 7 (February 20) |
3-D Model |
| 8 (February 27) |
Analysis of Structure/ Make Changes |
| 9 (March 6) |
Spring Break |
| 10 (March 13) |
Coordination of Trades |
| 11 (March 20) |
Heat Rejection |
| 12 (March 27) |
Clean-up Design/ Begin Final Presentation |
| 13 (March 3-5)) |
Prepare Final Presentation |
Task Schedule
A more in depth list of tasks to be completed can be found
here.
User Note:
Note: While great efforts have been taken to provide accurate and complete information on the pages of CPEP,
please be aware that the information contained herewith is considered a work-in-progress for this thesis project.
Modifications and changes related to the original building designs and construction methodologies for this
senior thesis project are solely the interpretation of Caitlin Ferrell. Changes and discrepancies in no way
imply that the original design contained errors or was flawed. Differing assumptions, code references, requirements,
and methodologies have been incorporated into this thesis project; therefore, investigation results may
vary from the original design.