| Date | Announcement | 
| 04.12.06 | Thesis Presentation posted | 
| 04.06.06 | Final Report updated | 
| 04.03.06 | Final Report posted | 
| 01.16.06 | Schedules posted in Progress Log | 
| 01.16.06 | Proposal revisions posted | 
| 01.11.06 | Breadth revisions posted | 
| 12.09.05 | Thesis Proposal posted | 
| 11.21.05 | Tech 3 and Executive Summary posted | 
| 10.31.05 | Tech 2 posted, Executive Summary posted | 
| 10.10.05 | Tech 1 Executive Summary posted | 
| 10.05.05 | Tech 1 posted | 
| 09.25.05 | Thesis Abstract posted | 
| 09.19.05 | Building Statistics posted | 
| 09.14.05 | Created e-portfolio webpage | 
| 08.31.05 | Started 5th year classes | 
Planning Schedule
- January
 
- 12 - Learn BLCC4
 
16 - Updated Proposal Due
17 - Parallel Systems
30 - Run-Around Heat Recovery System
31 - Progress Check
February
- 06 - Guest Rooms IAQ
 
20 - Lighting Breadth Work
27 - Acoustics Breadth Work
28 - Progress Check
March
- 13 - System Integration and Comparisons
 
15 - Table of Contents
20 - Finish All Unresolved Issues
27 - Write Final Report
April
- 03 - Final Report Due
 
10 - 1st Round of Presentations
28 - AE Banquet
Detailed Schedules
To view the Detailed Schedule for entire semester, please click here.
To view the Detailed Schedules for each month, please click on the following links.