Rendering Courtesy of IKM  

STRUCTURAL OPTION

WESTINGHOUSE ELECTRIC COMPANY
CORPORATE HEADQUARTERS
CRANBERRY, PA

 
 
 
 

BUILDING STATISTICS

BUILDING NAME: WESTINGHOUSE ELECTRIC COMPANY
CORPORATE HEADQUARTERS

BUILDING LOCATION: 1000 WESTINGHOUSE DRIVE, CRANBERRY PA

OCCUPANT: WESTINGHOUSE ELECTRIC COMPANY

BUILDING FUNCTION: OFFICE AND CORPORATE HEADQUARTERS

BUILDING SIZE: 434,800 SQ. FT

BUILDING HEIGHT: 5 STORIES 87'-6" TO TOP OF ROOF

DATES OF CONSTRUCTION: FEBRUARY 2008--TBD

PROJECT COST: $80 MILLION

PROJECT DELIVERY METHOD: DESIGN-BID-BUILD

MAJOR NATIONAL CODE MODEL:  IBC 2006

ELECTRIC AND FIRE CODES: NFPA 70, NECA, NEMA, UL

NFPA STANDARDS: 780, LPI-175, IEE-80, UL-96

WATER AND SEWAGE: STILL RESEARCHING

ZONING:

BUILDING HEIGHT: 87'6" TO THE PENTHOUSE PARAPET

BUILDING MAX HEIGHT: STILL RESEARCHING

CONSTRUCTION TYPE: 2A

BASELINE AREA: 37,500 SQ FT

HISTORICAL REQUIREMENTS OF BUILDING: NONE


PROJECT TEAM DIRECTORY

ROLE FIRM
OWNER

WELLS REAL ESTATE FUNDS
6200 THE CORNERS PARKWAY, SUITE 250
NORCROSS, GA 30092

TENANT WESTINGHOUSE ELECTRIC COMPANY
4350 NORTHERN PIKE
MONROEVILLE, PA 15146
STRUCTURAL/
MECHANICAL
ENGINEER
LLI ENGINEERING
6000 BROOKTREE ROAD
SUITE 300
WEXFORD, PA 15090
ARCHITECT IKM, INC.
ONE PPG PLACE
PITTSBURGH, PA 15222
CIVIL ENGINEER

CIVIL & ENVIRONMENTAL CONSULTANTS, INC.
333 BALDWIN ROAD
PITTSBURGH, PA 15205

CONSTRUCTION MANAGER TURNER CONSTRUCTION COMPANY
TWO PNC PLAZA, 27TH FLOOR
620 LIBERTY AVE.
PITTSBURGH, PA 15222

 

ARCHITECTURAL DISCUSSION

The Westinghouse Electric Company Headquarters is part of a campus with 2 other buildings on 83 acres in Cranberry, Pennsylvania.  The campus is at the back of a large office complex.  Building one is the main building containing the executive conference rooms, employee cafeteria and kitchen, fitness center, and data center. The remaining buildings are primarily office space.  The site has volleyball and basketball courts, bioretention for the parking lot, sidewalks between the buildings and around the lot as well as asphalt walking trails, and landscaping. 

The main building will utilize a powerful entrance with a two story atrium with the employee cafeteria beyond the entrance.  Polished concrete block will accentuate the base of the columns in the building while aluminum curtain walls will add light and help to open up the building.  The office buildings have a floor-to-floor height of 14’-0” for optimal tenant customization and the entrance has a height of 18’-0”.

 

BUILDING ENVELOPES

The Westinghouse Electric Company Headquarters Building is a steel framed building with a composite 22 gauge metal deck floor and lightweight concrete.  Up to the first 28’-8” there is an 8” polished concrete block on the exterior of the building with an R value equal to 11.0 and above that there is a brick veneer with the same R value.  Beyond the exterior there is an air space, 2” R.B. insulated sheathing, and 12” concrete backup block.  On the interior there is 4” polished concrete block, 6” cold rolled steel framing up to the second floor.  On the second floor and above there is gypsum wall board in front of cold rolled steel framing. 

Typical Roof construction includes a Thermoplastic membrane series, an exterior with an R value equal to 33.0, which includes rigid insulation and ½” protection board.  There is also a fully adhered EPDM roofing system including the membrane over 1/2" protection board, over tapered insulation over 5/8" type X GWB over the roof decking. The EPDM system is between the outside edge of the D and B.3 horizontal column lines and the left of column line 2 and to the right of column line 27.  All the materials have been chosen keeping in mind the LEED certification the building owner wishes to achieve. 

BUILDING SYSTEMS

 

STRUCTURAL

The foundation system of the Westinghouse Electric Company Corporate Headquarters is caisson driven with 67 caissons, spread footings or grade beams where there are no caissons.  Above the caissons, there is a 2’-6” cap with #6@ 8” c/c each way top and bottom and base plates for the columns.  The caissons were designed to carry 8,000 psf.  The grade beams carry the load from the exterior wall down to the foundation.  These grade beams have bottom, top, and end bars as reinforcement. 
Westinghouse Electric Company Corporate Headquarters has a typical composite floor system.  The composite action is created with 2”-22 gage steel deck with 2 ½” lightweight concrete slab on top.  3/4” diameter 3-1/2” long headed shear studs are used to secure the deck.  The deck also has 6x6 W2.1xW2.1 welded wire fabric reinforcement.  The deck is supported by steel joists and wide flange beams.  The wide flange beams in the Westinghouse Electric Company Corporate Headquarters Building One range from W12-W24 and the columns are mainly W14 but depending on location, some columns are size W10.  There are column splices above the second and third floors, and columns on the penthouse.  The beams in the system span 45’ maximum. 
The roof system is typically comprised of K series joists supported by wide flange beams and steel columns.  The deck is 22 gage 2” metal deck and has a 2-1/2” light weight concrete slab on top of it.  The roof supports mechanical units and cooling towers. 

 

CONSTRUCTION

The construction for the Corporate Headquarters Began in February 2008 and is scheduled to be turned over to the owner in May of 2009.  Turner Construction is the Construction Manager.  The Project will be delivered in a Design-Bid-Build method. 

 

MECHANICAL

The Mechanical System In Westinghouse Electric Company Corporate Headquarters Building One Was Designed With LEED Certification In Mind.  The System Uses 100% Outdoor Air And Is Digitally Controlled.  There Are Six Air Handling Units for the Building And Also Six Return Fans.  Two Gas Fired Boilers Serve To Heat The Building With Capacities Of 1265 CFM And 960 CFM.  The Heat Exchanger Must Be 95% Efficient While Maintaining 900,000 BTU Input and 846,000 BTU Output On A 480 V 3-Phase System.  The Three Cooling Towers Assist In The Temperature Control Of The Building And Are Located On the Roof.  The Corporate Headquarters Also Comes Equipped With A Snow Melting System Capable of 250 BTUH Per Square Foot at 130˚ F.

LIGHTING AND ELECTRICAL

Power to The Westinghouse Electric Company Corporate Headquarters Is Provided By Penn Power At 480 Y/277 V.  Power Is Provided with 3-Phase 4 wire and is stepped down to 208/120 3-Phase 4 wire for receptacles and lighting.  The two types of transformers present:  480/277V 3-Phase 3-Wire Primary and 208/120V 3-Phase 4-Wire Secondary Delta-Wye Dry Type Transformers.  There are generators present on the campus to provide extra protection.
Standard lighting is on each floor and standard patterns with emergency lighting is also on each floor.  The building also utilizes ad security system with acard swipe access.  Fluorescent lighting is prevalent in the lighting system. 

 

FIRE PROTECTION

The Westinghouse Electric Company Corporate Headquarters has a hydraulically designed wet pipe sprinkler system to cover all areas of the building.  Designed to NFPA Standards, the system includes all piping, alarm valves, and sprinkler heads.  Types of sprinkler heads include brass suspended ceiling, chrome plated upright, and enamel horizontal sidewall. 

 

TRANSPORTATION

The main entrance to the Westinghouse Electric Company Corporate Headquarters Campus is on Cranberry Woods Drive in an office park making entering the campus easy.  The main entrance lobby has the elevators for the building in it.  Electric traction elevators made by ThyssenKrupp are in use in the building.  Otis Elevator Company or Schindler Elevator Corporation models SPF-35 and SPF-50 are also present.  A Holed Hydraulic Elevator made by Otis, Schindler, or ThyssenKrupp is required for Building One. 

 

TELECOMMUNICATIONS

Telephone service is provided to each floor of the building is various locations.  The system is comprised of empty conduit and raceway to each location. 

 

 

 

 

 

 

 

 

courtesy of IKM

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Exterior Facade

 

 

 

 

 

 

 

East Side of Building One

 

 

 

 

 

 

 

West Side of Building One

 

 

 

 

 

 

 

Center of Buidling One

 

 

 

 

 

 

 

Basement of Building One

 

 

 

 

 

 

 

Bioretention in Parking Lot


 


 

 

 

           
SENIOR THESIS THE PENNSYLVANIA STATE UNIVERSITY DEPARTMENT OF ARCHITECTURAL ENGINEERING AE COMPUTER LABS CONTACT JESSICA L. LAURITO

The Capstone Project Electronic Portfolio (CPEP) is a web‐based project and information center. It contains material produced for a year‐long Senior Thesis class. Its purpose, in addition to providing central storage of individual assignments, is to foster communication and collaboration between student, faculty consultant, course instructors, and industry consultants. This website is dedicated to the research and analysis conducted via guidelines provided by the Department of Architectural Engineering. For an explanation of this capstone design course and its requirements click here.


THIS PAGE WAS LAST UPDATED ON SEPTEMBER 4, 2008 , BY JESSICA L. LAURITO AND IS HOSTED BY THE AE DEPARTMENT © 2008