bsaarch

Dan Vallimont

2009 Construction Senior Thesis
Santa Rosa Junior College Student Center
Santa Rosa, California

Thesis Proposal

 

 

 

Thesis Proposal

ORIGINAL THESIS PROPOSAL

REVISED FINAL THESIS PROPOSAL

The following proposal is intended to give glimpse of the four topics that will be researched and analyzed for a final thesis project on the Santa Rosa Junior College Student Center project.  The four different areas include the use of building integrated renewable energy as an additional sustainability element, constructability and cost impacts of alternative façade systems, cost and schedule impacts of an alternative steel erection process, and the impact of an alternative prefabrication process as it is related to the precast concrete elements of the student center.

Critical Industry Issue

With energy costs continually on the rise, taking advantage of new building integrated renewable energy systems seems like a great solution.  In the case of the SRJC student center it makes even more sense since the project is located in a geographic region that receives a large amount of sun annually.  Although it would require a steep upfront cost, utilizing some form of renewable energy system would surely benefit the owner with its long term payback.

Analysis 1

Construction of the brick façade proved to be a challenging task due to the fact that the brick supports were attached to metal studs as well as steel members to tie the façade into the structure.  Having two types of connections caused confusion during construction.  Also, the connections to the structural steel were very difficult to weld, causing much time and money to be wasted.  I believe that the use of a single type of connection would have sped up construction and minimized delays while saving money.

Analysis 2

The steel erection process used for the student center resulted in nearly three months of delays that resulted in excess spending.  A single mobile crane and connection crew were used to complete the entire steel frame of the building, resulting in the need for a 72 day deadline extension.  I believe that the use of multiple cranes and crews would have resulted in the structural frame being completed on time without a negative cost impact.

Analysis 3

The design-build prefabrication process used for the architectural panels on the student center resulted in incorrectly sized members due to the fact that exact field measurements were never able to be taken.  I believe that the use of an alternative option such as design-assist would have resulted in a more efficient process that would lead to simplified installation and furthermore reduced cost and schedule impacts.

 

 

 

Breadth Topics

BREADTH TOPIC ANALYSIS

The following topics take a look into the technical options within the architectural engineering major which will be investigated through a detailed analysis.  Both of the topics mentioned relate to the previously mentioned, Building Integrated Renewable Energy, section of this proposal.

Technical Analysis 1:  Architectural


The architectural design of the SRJC student center was one of the primary concerns of the owner from the very beginning.  That being said, the idea of “ruining” the owner’s vision of the building by placing solar panels on the tile roof for use with a building integrated renewable energy system poses a problem with the current design.  The current roof design has very little flat space, thus making nearly every inch of the tiled design visible from ground level by pedestrians.  Placing solar panels on the current roof has been deemed unacceptable by the owner solely on the fact that being able to see the panels on the roof would compromise the architecture that the SRJC has envisioned.
This analysis aims at finding a way to redesign the current roof to meet the owner’s architectural standards while also permitting space for solar panels that will be needed in the proposed renewable energy system for the student center.


Technical Analysis 2: Structural      


The current structural system of the SRJC student center supports a roof comprised of concrete tiles that are fastened to two layers of 30 pound self-adhering asphalt saturated felt.  This structural system was designed without the addition of a large solar array calculated into the loading. 
This analysis will involve calculating the effect of a large solar array on the existing structural system and then comparing that to the maximum load allowed under the current system.  Should the maximum load be exceeded by the solar panels, I will need to develop a way to further support the roof of the student center through an in-depth look at the structural system which would focus on ideas such as alternative member sizes, added reinforcement, etc.

 

Revised Technical Analysis 2: Electrical

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The Capstone Project Electronic Portfolio (CPEP) is a web-based project and information center. It contains material produced for a year-long Senior Thesis class. Its purpose, in addition to providing central storage of individual assignments, is to foster communication and collaboration between student, faculty consultant, course instructors, and industry consultants. This website is dedicated to the research and analysis conducted via guidelines provided by the Department of Architectural Engineering. For an explanation of this capstone design course and its requirements click here.

 

 

 

Senior Thesis | The Pennsylvania State University | Architectural Engineering | AE Lab | Contact STUDENT |
This Page was last updated on April 27, 2010 , By Student Name and is hosted by the AE Department ©2005