Note: While great efforts have been taken to provide accurate and complete information on the pages of CPEP, please be aware that the information contained herewith is considered a work-in-progress for this thesis project. Modifications and changes related to the original building designs and construction methodologies for this senior thesis project are solely the interpretation of Monjia Belizaire. Changes and discrepancies in no way imply that the original design contained errors or was flawed. Differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the original design.

 
 
 

 

Welcome to Monjia Belizaire's AE Senior Thesis e-Portfolio!

 

Thesis Research


RESEARCH TOPIC - Building Information Modeling-3D

Methodolgy

  1. Review literature on BIM-3D modeling.
  2. Conduct phone interview with Jan Reinhardt, the Program Manager of ViCon - Virtual Design and Construction, at Turner Construction.
  3. Attend a 3D modeling coordination meeting with Paul White, MEP coordinator on Phase 2 of the City Hospital project and subcontractors to get an understanding of some of the issues faced and how these issues could have potentially been eliminated during Phase 1 between trades during the construction phase if BIM was used.

TECHNICAL ANALYSIS 1 - IMPLEMENTING LEED® GOLD CERTIFICATION

Methodolgy

    1. Literature review to become familiar with the different LEED® points
    2. Review the LEED® points that are intended to be achieved on the project
    3. Review potential LEED® points with LEED® consultant, Gabriella Edwards on the City Hospital project
    4. Identify four LEED® additional points for Gold Certification (includes SS Credit 6.2)
    5. Investigate the implementation of SS Credit 6.2: Stormwater Design: Quality Control which includes research options such as limiting the disturbance of natural water hydrology by managing stormwater runoff.

    TECHNICAL ANALYSIS 2 - IMPLEMENTING MEDIUM VLOTAGE GENERATOR

    Methodolgy

    1. Review literature on using medium voltages on construction projects
    2. Review case studies of Hospitals that uses Medium voltage
    3. Review City Hospital electrical drawings and specifications for information about the (2) 2MW diesel generators
    4. Conduct an analysis using 4160V generator
    5. Compare costs, installation, materials used between existing system and 4160V analysis

     

     

     

     

     

  •    