While great efforts have been taken to provide accurate and complete information on the pages of CPEP, please be aware that the information contained herewith is considered a work-in-progress for this thesis project. Modifications and changes related to the original building designs and construction methodologies for this senior thesis project are solely the interpretation of Nasser Marafi. Changes and discrepancies in no way imply that the original design contained errors or was flawed. Differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the original design.
 



THESIS PROPOSAL

Executive Summary

During the upcoming semester, a complete redesign of the main lateral force resisting system will be performed using steel eccentrically braced frames. The redesign will evaluate the economical implications of using this system as opposed to the concentric braces designed in the original design. The breadth study will then evaluate the cost and scheduling effects of the redesign and comparisons will be made to the original design. The final breadth study will be a lighting redesign of the central courtyard located on the second floor, which will evaluate the use of the space during the day and night before and after the redesign. 
These tasks will have major outcomes after being performed and will prepare my skills for the start of my career in structural engineering as well incorporate my creative skills that I have gained throughout the pursuit of my degree. 

Click here to download the full version of the revised proposal on 01/18/08 in PDF format.

Click here to download the full version of the proposal in PDF format.

Click here to download the executive summary with breadth study in PDF format.

Breadth Studies Revised on 01/18/08

Construction Managment Breadth Study

The decision to use eccentric braced frames would have impact on scheduling and construction cost. Therefore a detailed cost analysis would have to be done to see how much money would have been saved if this system was first implemented. The addition of moment connections required at the columns and the beams would have impact of construction time, therefore this design would require a detailed scheduling analysis to be done so that a recommendation can be made regarding if this system provides the optimal solution.

Lighting/Electrical Breadth Study

The second floor court yard will be looked at with light approaching in during the day and night time conditions. Appropriate light fixtures will be selected and placed at areas to accentuate architectural features and landscaping at the courtyard space. The lighting fixtures will help provide the use of outdoor space that is safe for the patients while not distracting patient rooms that are facing the court yard space.  The courtyard is also visible from the north face of the building. Therefore the overall effects on the building’s front façade will be analyzed and incorporated into the final lighting design. The space will be modeled using AGI-32, a lighting design software for calculations and visualizations.  This will provide renderings of the final design that can be presented to the client for approval.

 

 

 


 

   
           
 