Welcome to a presentation of Matthew J. Decker's Senior Thesis project. The work presented on these pages represents an on going in depth study of the Massachusetts General Hospital "Building for the Third Century" Project. The Studies presented on the following pages represent a focus on the structural systems of the building. Progress on this task is located in the table below:

Date
Progress
Date
progress
8.25.08
5th Year Begins
12.12.08
Proposal posted
8.29.08
Web site work
1.20.09
Revised PRoposal
9.03.08
Documents recieved
1.21.09
Consultation Boothby
9.22.08
Student Bio Posted
2.1.09
Discussion Board Used
10.6.08
Tech 1 posted
2.23.09
Progress 50%
10.13.08
Building Stats posted
3.16.09
Milestones met
10.27.08
Tech ii Posted
4.7.09
Final Report Submition
11.23.08
Tech iii posted
4.14.09
Final Presentation

 

Home_Button
 

. PENN STATE E-STUDIO . THE PENNSYLVANIA STATE UNIVERSITY . ARCHITECTURAL ENGINEERING .
. CONTACT .

Note: While great efforts have been taken to provide accurate and complete information on the pages of CPEP please be aware that the information contained herewith is considered a work-in-progress for this thesis project. Modifications and changes related to the orginal building designs and construction methodologies for this senior thesis project are solely the interpretation of Matthew J. Decker. Changes and discrepancies in no way imply that the orginal design contained errors or was flawed. Differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the orginal design.

This page was last updated on Monday, February 2, 2009 by Matthew J. Decker and is hosted by the AE Department © 2008