Building name-The  Concordia 
            Location and site-Washington, D.C. The specific address cannot be  used 
             
              
            
            Architecture 
            
              Architecture (Design and functional components)-The Concordia is a 10-story plus cellar and  underground parking garage extended stay facility with two main structures  connected at the ground floor. While the entire building is composed of 178  rooms the bond building has 78 while the Concordia houses the other 100. It was  designed in by Berla & Able. 
              Major national model codes (IBC 2003, BOCA 1999)  
              IBC 2006/DCMR 12A-2008 
              IBC 2006/DCMR 12E-2008 
              IPC 2006/DCMR12F-2008 
              NFPA NEC 2005/DCMR 12C-2008 
              IFC 2006/DCMR 12H-2008 
              IFGC 2006/12I-2008 
              IEBC 2006/DCMR 12J-2008 
              ANSI 117.1-2003/DCMR 12A Chapter 11 
              DCMR Title 11-zoning regulations 
              District of Columbia Environmental Policy Act of  1989 
              Green Building Act of 2006 
              Zoning 
              DC/R-5-E Overlay (http://maps.dcoz.dc.gov/#)  
             
              
            
              Historical requirements of building or  historical district where built.  
              In 1965 the IMF Concordia was designed by Berla  & Able. The building is neither in a historical district nor are there  historical requirements for salvaging portions of the building or the building’s  façade.  
             
            Building enclosure 
            Building facadesExterior wall type # 12 consists of 6” Batt  insulation, 5/8” thick exterior sheathing, liquid applied air barrier, 2” rigid  insulation, aluminum clip, sealant with backer rod and shims where required.  The last layer to make up the wall is the aluminum composite material  panel.    
              
            Exterior wall type # 14 will be composed of  7-5/8” thick Concrete Masonry Units (CMU) with a liquid applied air barrier,  Z-channel fasteners @ 16” O.C., 2” moisture resistant rigid insulation,  required shim to separate aluminum channel from Z-channel, max shims ¾” thick,  weeped calcium silicate channel, and finally a calcium silicate masonry unit.     
              
            Exterior wall type # 15 has 7-5/8” thick CMUs  while wall type 15a has 11-5/8” thick CMUs. They have essentially matching  components which include liquid applied air barriers, 2” rigid insulation, aluminum  clip, sealant with backer rod and shims where required. The last layer to make  up the wall is the aluminum composite material panel.    
              
            Exterior wall type # 16 has 5-5/8” CMUs, liquid  applied air barrier, 2” rigid insulation, 3-5/8” CMU, and lastly metal anchors.  
              
            The building façade has an Aluminum Trellis’ and  aluminum panels with aluminum coping.   
              
            
              Roofing 
              The roof is composed of tapered insulation with  a 2” base and a single ply membrane both of which rest on the existing slab. 
             
              
            The live planter roofing will consist of a  liquid applied air barrier installed on top of the existing slab which will be  followed by much thicker tapered insulation, a single ply membrane and lastly  live roof planter beds.   
               
            Sustainability  features 
            Due to the outdated inefficient systems which were installed  when the building was completed this renovation will gut and renovate all the  major MEP systems. The renovation of the IMF Concordia is planning to achieve a  LEED Gold certification. The goal of achieving this certification will be  dependent on the many systems of the structure coming together to produce an  efficient building.  
            
              Plumbing 
              The renovation of The Concordia’s will include the  installation of Domestic Booster Pumps in order to help produce a more  efficient, energy saving plumbing system.  
              Electrical 
              Turner’s renovation of the Concordia will  include the installation of LED down lights in many of the corridors as well as  many other LED fixtures throughout the building. 
              Mechanical 
              This renovation will make the building’s  mechanical system more efficient by installing 100% outside air packaged energy  recovery air handling units and 100% outside air makeup air units 
              The mechanical system will be improved  drastically by installing Variable Refrigerant Volume (VRV) systems. (http://www.mechanicalservicesfiji.com/vrv_aircon.html)  
             
              
            
              Roofing 
              The bay roof will have live roof planter beds in  order to help reduce the heat island effect as well as storm water runoff. 
             
              
             
            Part 2 
             
              The  renovation of the Concordia Hotel requires the demolition of the entire MEP  and Architectural systemsand lastly some of the Structural systems and the extensive amount of Architectural  systems. The structure is located in the heart of Washington D.C., the specific  address has been purposely withheld due to owner’s requests. The project is located near Dupont Circle. The Whiting-Turner Construction Company is the General Contractor (GC) responsible on the renovation project of the outdated fifty plus year old structure.  
             
              Since  the project is located in a very urbanized area, a detailed construction plan, sequence  and schedule will be utilized for the Concordia Hotel to ensure timely project  completion. The construction process will begin with the demolition of all the  existing interior and exterior walls and the extensive architectural façade. This  demolition will also include the removal of the stair/elevator core of the  structure. Once demolition and asbestos abatement is complete, the rehabilitation  of the foundation will begin. This rehabilitation will continue up and  throughout the structure and consist of the construction of new beams, columns,  and slabs as well as the rehabilitation of key slabs throughout the building.  The construction project was planned to be handed over to the owner in December  23rd, 2012 this handover date has been pushed back extensively due  to technicalities with construction. 
               
            Electrical/Lighting 
              The  electrical system will consist of 13 transformers. The sizes of these  transformers are a 3, 6, 9, 15, 30, 45, 75, 112.5, 150, 225, 300, 500 and 750  KVA transformers. There will be 28 panel boards located throughout the building  faced with the task of providing power to equipment and systems located on each  floor in different regions of the structure. The main utility electric will  come in from the eastern side of the structure and travel into the main  electrical room located in the cellar of the structure. In the main electrical  room (located in the cellar) the electric will be fed into the Main switchboard  (MS-1), a 4000A 208/120V-3phase 4W 100KAIC system which will distribute  electric to the remainder of the building. MS-1 will then provide power to  DPR-1 which will provide service to the LPR-1 and the LP-POOL for the major  pool equipment. MS-1 will also service DPC-1, DPL-3, SLPC-1ELPC-1 and AHU-2  located on the roof of the structure. The electrical system will have a 15 KVA  Uninterruptable Power Supply (UPS) system utilizing an Automatic Transfer  Switch (ATS) and a generator located in the garage level of the structure.  Turner’s renovation of the Concordia will  include the installation of LED down lights in many of the corridors as well as  many other LED fixtures throughout the building. 
              
               
               
              Mechanical 
              The  mechanical system will consist of two Air Handling Units (AHU); responsible for  conditioning and circulating the air for the entire building and one Makeup Air  Unit (MAU) for providing supply air for the building. AHU-01 will be a 100 %  outside air packaged energy recovery AHU which will be electric heat. In figure  18 the AHU-01 is highlighted in blue, it will be located in the mechanical room  cellar and it will service the ground level. The detail and location of AHU-01  is shown in figure 19. AHU-02 will also be a 100 % outside air packaged energy  recovery AHU; however, it will be gas heat. AHU-02 will be located on the  rooftop and will be responsible for servicing the guestrooms its location is  shown highlighted in yellow in figure 22 and the mechanical section is shown  highlighted in yellow in figure 23 as well. MAU-1 will be a 100% outside air  MAU which will be indirect gas-fired and it will be located in the cellar level  in the same location as AHU-01 shown highlighted in red in figure 18. The MAU  mechanical section is shown in figure 19 with the MAU highlighted in red. I  have attached product information for the AHU-01, AHU-02 and the MAU-1 below in  figures 20, 21 & 24. The building will have nine (9) fans for the many  areas requiring ventilation which will be five (5) supplies, one (1) exhaust, one  (1) return and two (2) exhaust/returns. As I stated in my Building Statistics  there will be new Variable Refrigerant Volume (VRV) systems installed into the  structure as well as eleven (11) VRV air cooled condenser outdoor units located  on every floor, and three (3) air cooled split system located in the fire  control room the IT/telecom room and the elevator control room. Lastly, there  will be two (2) electric unit heaters and one (1) relief hood.  
                 
     
     
     
              Structural 
              The  Concordia Hotel was constructed in 1965, the structure consists of Cast-In-Place  (CIP), non-post-tensioned slabs. The renovation of the Concordia includes the  extensive rehabilitation of the structural systems throughout the structure. The  rehabilitation of the structure includes improvements to the foundation,  columns, beams and slabs. These rehabilitation techniques were applied to the  structure in order to compensate for layout changes and the installation of two  new stairwells. This rehabilitation of the structure begins in the cellar level  and consists of the installation of 78 Micro Piles with 42 inch thick mat  slabs. The elevation to the bottom of exterior footings is a minimum of 2’-6” below  finished exterior grade in most areas and in others is defined on the structural  drawings. The cellar level Slab-On-Grade (SOG) is typically 5-8”. The rehabilitation  continues above on floors 1-10 and includes slab strengthening techniques which  include the installation of several new column types, beam types and the  application of Carbon Fiber Reinforcement Panels (CFRP) to both the bottom and  top of the slabs. The beam schedules and CFRP layouts are included below. These  beams support the roof which also supports the high roof which houses a  mechanical room and several crucial mechanical systems.  
             
            First Floor  Beam Schedule (New Construction) 
                
            Even  & Odd Floor (Floors 2, 3, 4, 5, 6, 7, 8, 9, 10) Beam Schedule (New Construction)  
               
             
              High  Roof Beam Schedule (New Construction)  
                 
              The  installation of the CFRP panels will typically be installed to the even floors  above and below the slab to increase the structural integrity of the slabs.  
                 
            Fire Suppression 
             
              The fire  suppression system that will be used is a combination of a wet-pipe system and  a dry-pipe system in areas where the freeze thaw cycle is likely to occur. A  Peerless model T41 jockey pump combined with a Peerless Model 6AEF10 Horizontal  Splite Case Fire Pump. The pump and jockey pump will distribute water to the  sprinkler system and maintain water pressure throughout the building. The loading  dock will have a dry pendant fire sprinkler system (based on winter freezing  conditions) connected to the wet-pipe system located in the heated ceiling  space. Details are provided below of typical pendant style sprinkler heads. All work shall be installed in accordance with NFPA 13, 14, 20, and all other applicable codes.  
               
            Transportation 
            The existing elevator core had only two elevators, one freight elevator and one passenger elevator. The existing core was removed to make  room for the new elevator core which would have three elevators. The Concordia Hotel has two passenger elevators and one freight elevator. 
            The existing stair well/elevator core has been demolished and two new stairwells have been installed. This installation required the strengthening of key slabs through the construction of several beams, columns and CFRP. The new construction of the two stairwells will be located on either side of the structure.  
            Telecommunications 
            Due to the structure being an extended stay type hotel there will be security rooms and security systems installed to limit the building access only to approved hotel guests. The project will also have key audio visual/information technology equipment to provide guests with the capabilities that they desire.  
           |