Note: While great efforts have been taken to provide accurate and complete information on the pages of CPEP, please be aware that the information contained herewith is considered a work‐in‐progress for this thesis project. Modifications and changes related to the original building designs and construction methodologies for this senior thesis project are solely the interpretation of Matthew Moore. Changes and discrepancies in no way imply that the original design contained errors or was flawed. Differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the original design.
 

 

 
Research

Research

The research that was done for this thesis is on Short Interval Production Scheduling, (SIPS). Within this document you will find background on SIPS and well as the methodology about how to develop a successful schedule. It describes that step by step process which will guide you to developing a SIPS:

  1. Break the operation into specific activities
  2. Assign production rates to each activity
  3. Calculate extensions and set goals
  4. Develop a time-scaled, resource loaded bar chart

 

 

  SENIOR THESIS E-STUDIO | THE PENNSYLVANIA STATE UNIVERSITY | ARCHITECTURAL ENGINEERING | AE COMPUTER LAB | CONTACT ME

  This page was last updated on April 9, 2008 by Matthew Moore and is hosted by the AE Department ©2007