Final Report

Download Document Go to Executive Summary >>

Summary

This report provides deatailed overviews of four technical alnalyses conducted for the
LancasterHistory.org project that involves a renovation and addition to the existing Lancaster Historical Sociaety Building loacated in Lancaster, Pennnsylvania. These analysyes include a critical industry research topic and demonstrate two breadth ares.

The four technical analyses provided in this report include:

1. A study of soil remediation effects on constructability and schedule
2. A review of whether a conventional mechanical system would be more cost effective than an open‐loop geothermal system
3. An examination of whether the application of MEPF prefabrication would increase constructability and shorten the project schedule
4. An analysis of whether a greater use of Building information Modeling could have benefitted the parties during the project

The study of soil remediation is conducted because unsuitable soils caused construction issues and schedule delays early into the project. This analysis includes critical research in the form of a case study to show the importance of a well conducted geotechnical report. Also, it includes a structural breadth regarding subsurface design. The analysis shows that an alternate soil remediation approach is the best resolution.

The second analysis investigates LH.O’s potential for a conventional mechanical system to replace its geothermal one, considering value. This is because the geothermal system had not been able to meet performance requirements at the time of the investigation. The analysis includes a mechanical breadth regarding value. The implemented open loop geothermal is found to have a much higher initial cost, but has much lower future annual energy costs.

Application of prefabrication presented an opportunity for LH.O because its MEPF systems are fairly complex. It is discovered that plumbing and electrical systems lend themselves to prefabrication, and it is determined that various electrical assemblies could be prefabricated in order to reduce construction schedule and improve constructability.

The final analysis detailed in this report considers a greater use of BIM on LH.O. This analysis is intended to increase value for the project. A greater use of seven BIM utilizations in pre-construction and in construction is deemed valuable from a cost and constructability standpoint.

"Note: While great efforts have been taken to provide accurate and complete information on the pages of CPEP, please be aware that the information contained herewith is considered a work-in-progress for this thesis project. Modifications and changes related to the original building designs and construction methodologies for this senior thesis project are solely the interpretation of Eric Buckwalter. Changes and discrepencies in no way imply that the original design contained errors or was flawed. Differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the original design."