Technical Assignments

Tech 1

Tech 1 is posted here.

This report is an analysis of the current design and construction of the Pershing Hill Elementary School Replacement Project at Fort Meade, MD. It includes a summary schedule, building systems overview, project cost evaluation, site plan of existing conditions, and analysis of the local conditions, client information, project delivery system, and staffing plan.

Tech 2

Tech 2 is posted here.

This report is an analysis of the schedule, site layout, structural and general conditions costs for the Pershing Hill Elementary School Replacement Project at Fort Meade, MD. It includes a detailed project schedule, proposed site layout plans, detailed structural system estimate, and a general conditions estimate. In addition, this report contains a summary of critical industry issues discussed at the annual PACE Roundtable Meeting.

Tech 3

Tech 3 is posted here.

This report identifies several features of the Pershing Hill Elementary School Replacement Project at Fort Meade, MD that are good candidates for further research next semester. It includes an analysis of the constructability challenges, schedule acceleration scenarios, and value engineering for the project.

Note: While great efforts have been taken to provide accurate and complete information on the pages of CPEP, please be aware that the information contained herewith is considered a work-in-progress for this thesis project. Modifications and changes related to the original building designs and construction methodologies for this senior thesis project are solely the interpretation of Mitchell Reiners. Changes and discrepancies in no way imply that the original design contained errors or was flawed. Differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the original design.