maggie.mcnamara
mechanical

n.r.u.c.f.c.headquarters

building.statistics.

sterling, va
home
student.biography
building.statistics
thesis.abstract
technical.assignments
thesis.research
thesis.proposal
presentation
final.report
reflection
e-studio
   

Project Summary
Building Occupant |
National Rural Utilities Cooperative Finance Corporation (NRUCFC)
Type of Building | Office Building
Size | 120,000 GSF
Number of stories | 3 above grade
Construction Dates | November 2009- September 2011
Project Cost | $45 million
Project Delivery Method | Design-Bid-Build

 

Architecture
The NRUCFC Headquarters building incorporates traditional elements of Virginia architecture while also incorporating modern architecture styles. Set on a sloping topography and tucked in awooded area, the headquarters building is meant to be a secure and safe workplace for NRUCFC employees while portraying an image of openness and accessibility. The three story atrium serves as both a main architectural feature and an area to showcase energy saving mechanical and electrical systems.The first floor houses the main lobby/atrium, a gym, a cafe, an executive lounge, and an office area. The second and third floors are primarily office space.

 

   
Project Team
Architect | Kishimoto.Gordon.Dalaya PC
Interior Architect | Fox Architects
Landscape | EDAW
Site/Civil Engineers | Dewberry
Structural Engineers | SK&A
MEP Engineers | Flack + Kurtz
LEED Consultant | Sustainable Design Consulting
General Contractor | Whiting-Turner

Building Enclosure
Building Facades
The building facade is a curtain wall system that uses a combination of cast stone, aluminum panels, face brick, and spandrel, low-e glazing. The front of the building uses brick pre-cast panels and cast stone (pictured below), while the back of the building uses primarily glazing with shading devices as the facade (pictured above).
Roofing
Fiberglass reinforced thermoplastic membrane with a lacquer coating is used for the roofing. 2" rigid insulation is used. Reflective metal panels are used on the wings of the building to reflect the sunlight.

     

Applicable Codes
2006 Building Code (USBC)
2006 State Wide Fire Protection
2006 Mechanical Code
2006 Electrical Code
2006 International Building Code (IBC)
2003 ICC/ANSI A117.1
2006 National Electric Code (NFPA-70)
International Energy Conservation Code (with ASHRAE 90.1-2004)

Zoning
According to the Loudoun County Zoning Ordinance, 1972, the site on which the NRUCFC Headquarters is considered a PD-OP Planned Development - Office Park. It is required to be 150 feet from adjacent routes 7 & 28; 35 feet from all adjacent public streets; 25 feet from non-residential lot. The max building height allowed is 100 feet. 1 parking space per 375 SF of Net Floor Area is required.

Historical Requirements
There are no historical zoning requirements.

Sustainability Features
Building
NRUCFC Headquarters building is meant to “make a positive environmental impact, be cleaner, healthier, and more efficient.” The project is expected to achieve LEED(R) Gold certification with a score of 45 points. To make the building more energy efficient, special focus is placed on the building envelope, HVAC systems, and daylighting controls. A graywater system is installed to reduce the use of potable water. The use of geothermal energy reduces the energy demand of the building on the grid. Photovoltaic cells are used to collect solar energy to further reduce the demand on the grid.
Site
Low-water-demand and drought resistant vegetation is used to reduce the water demand. Carpooling and the use of low-emitting, fuel-efficient vehicles are encouraged and rewarded with preferred parking spaces. The use of bicycles is also encouraged. Bike racks and showers are provided to all building occupants.

 

 

Construction
The construction of the building began in November 2009 and was completed in September 2011. The project delivery method was Design-Bid-Build and the total project cost was approximately $45 million dollars.
 
Mechanical
The NRUCFC Headquarters building is conditioned by four roof top air handling units and each handle approximately 20,000 CFM. Each AHU serves a quadrant of the building. The interior spaces use VAV boxes while the exterior spaces use fan powered boxes. Both have hot water reheat capabilities. CO2 sensors are utilized throughout the building to determine the amount of outside air that needs to be sent to each zone.

The headquarters building is served by two high efficiency chillers. The absorption chiller, located in the Penthouse, serve six “ice on coil” storage tanks to use as cooling during peak hours. The building is heated by two high efficiency boilers located in the Penthouse.

 
Structural
The foundation consists of a combination of isolated columns and strip wall footings with a 5” slab on grade. The steel frame utilizes primarily W12x22 and W21x44 composite beams and a 2” composite slab on the second and third floors. The central atrium is formed by arched trusses made of HSS members which form a dome with an oculus.

 

  Lighting
A variety of fixtures and luminaires are utilized in the building. They are controlled by both daylighting sensors on the perimeter of the building and occupancy sensors. The furniture layout allows for maximization of daylighting within the cubicle space to decrease the lighting load.
 
Electrical
The electrical service is provided at 277/480V, 3 phase, 4 wire which will be transformed down on site. The distribution panels are located in the main electrical room on the first floor.
   

 

   
 
       
senior thesis main page | penn state university | architectural engineering department | ae computer labs | contact maggie mcnamara
this page was last updated on 1.17.12 by maggie mcnamara and is hosted by the ae department (c) 2011
*note: while great efforts have been taken to provide accurate and complete information on the pages of cpep, please be aware that the information contained herewith is considered a work-inprogress for this thesis project. modifications and changes related to the original building designs and construction methodologies for this senior thesis project are solely the interpretation of maggie mcnamara. changes and discrepancies in no way imply that the original design contained errors or was flawed. differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the original design.